C-TS422-1909 Exam Question 11
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:
C-TS422-1909 Exam Question 12
In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars indicate?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
C-TS422-1909 Exam Question 13
What is the first step in the MRP run?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
C-TS422-1909 Exam Question 14
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
C-TS422-1909 Exam Question 15
What new technology is used in SAP S/4HANA Embedded Analytics?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Premium Bundle
Newest C-TS422-1909 Exam PDF Dumps shared by Actual4test.com for Helping Passing C-TS422-1909 Exam! Actual4test.com now offer the updated C-TS422-1909 exam dumps, the Actual4test.com C-TS422-1909 exam questions have been updated and answers have been corrected get the latest Actual4test.com C-TS422-1909 pdf dumps with Exam Engine here: