C_TSCM42_67 Exam Question 1
Which of the following statements about the planning functions available in SAP ECC is correct?
C_TSCM42_67 Exam Question 2
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
C_TSCM42_67 Exam Question 3
Which of the following organizational efforts can be minimized using the KANBAN procedure?
C_TSCM42_67 Exam Question 4
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following properties for the resulting dependent requirements applies?
Which of the following properties for the resulting dependent requirements applies?
C_TSCM42_67 Exam Question 5
Which activity can trigger an automatic availability check for the components of a production order?