C_TSCM42_67 Exam Question 31

In which master data object do you set the standard values for an operation?
  • C_TSCM42_67 Exam Question 32

    You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
    On which specifications is the dynamic safety stock calculation based?
  • C_TSCM42_67 Exam Question 33

    Which of the following structural elements does a process order have? (Choose three.)
  • C_TSCM42_67 Exam Question 34

    A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order.
    The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
    What do you have to consider for the two lists at this stage? (Choose two)
  • C_TSCM42_67 Exam Question 35

    In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
    - Start: 7:00:00 a.m.
    - End: 3:00:00 p.m.
    - Break duration: 1 hour
    - Rate of utilization: 80%
    - Overload: 110%
    - Number of individual capacities: 1
    How large is the standard available capacity?