C_TSCM42_67 Exam Question 31
In which master data object do you set the standard values for an operation?
C_TSCM42_67 Exam Question 32
You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?
On which specifications is the dynamic safety stock calculation based?
C_TSCM42_67 Exam Question 33
Which of the following structural elements does a process order have? (Choose three.)
C_TSCM42_67 Exam Question 34
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order.
The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
What do you have to consider for the two lists at this stage? (Choose two)
The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
What do you have to consider for the two lists at this stage? (Choose two)
C_TSCM42_67 Exam Question 35
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?