A Solution Architect is presenting a design for the Phase 1 rollout of a B2B multi-cloud solution that includes CPQ and B2B Commerce using the CPQ B2B Commerce Connector. During the presentation, business stakeholders push bade on some of the key design aspects. The business is keen to have the product images and SCO data pushed back to CPQ from 828 Commerce, which is not incorporated in the current design. Further, the business wants the Solution Architect to find a way to map discounts and promotions in 828 Commerce to CPQ pricing and add that to the Phase 1 deliverables.
Which two responses should a Solution Architect present to the stakeholder s?
Choose 2 answers
Which two responses should a Solution Architect present to the stakeholder s?
Choose 2 answers
B2B-Solution-Architect Exam Question 7
Universal Containers (UC) needs to provide a portal for its customers to order spare parts for the equipment that has been sold to them. Spare parts orders are fulfilled in uC's ERP system and need to be integrated with the solution. Order status would need to be reflected in the solution. Additionally, m the future, UC wants this order integration scaled to additional applications. UC also needs customers to be able to schedule appointments for service for their equipment.
Which products should a Solution Architect recommend implementing to meet these requirements?
Which products should a Solution Architect recommend implementing to meet these requirements?
B2B-Solution-Architect Exam Question 8
Universal Containers (UC) is about to complete the first phase of its digital transformation with its new Lead to Invoice process that incorporates several clouds like Sales Cloud, Service Cloud, Revenue Cloud, Experience Cloud, and MuleSoft. UC is now creating a Center of Excellence and focusing on a purely Agile methodology for working on new releases. UC wants to understand some of the considerations around release planning.
What are two recommendations a Solution Architect should make to ensure UC's releases to production work within its release schedule and there are no delays in future releases?
Choose 2 answers
What are two recommendations a Solution Architect should make to ensure UC's releases to production work within its release schedule and there are no delays in future releases?
Choose 2 answers
B2B-Solution-Architect Exam Question 9
Ohana Cirrus (OC) has around 1,500 support agents working in its global support center operating 24/7 across multiple channels. This center handles around 30,000 cases per day. OC currently uses a custom-developed solution to manage customer complaints and is planning to replace it with a new Salesforce solution. The current system contains more than 250 million records including some still being processed.
Which three recommendations should a Solution Architect suggest to migrate to the new application in the most efficient manner?
Choose 3 answers
Which three recommendations should a Solution Architect suggest to migrate to the new application in the most efficient manner?
Choose 3 answers
B2B-Solution-Architect Exam Question 10
Refer to the images below:

As part of its solution to accelerate overall sales. Universal Containers (UC) has chosen to implement a CPQ solution using Salesforce CPQ. As part of the CPQ solution, there is a requirement to retain UC's ERP as the Pricing and Product master.
UC's business process results in Products and Pricing being updated sporadically once a week, and then on a much larger scale on a monthly basis, which could result in a large amount of records that need to be updated in Salesforce.
Which strategy should the Solution Architect choose to handle this scenario?

As part of its solution to accelerate overall sales. Universal Containers (UC) has chosen to implement a CPQ solution using Salesforce CPQ. As part of the CPQ solution, there is a requirement to retain UC's ERP as the Pricing and Product master.
UC's business process results in Products and Pricing being updated sporadically once a week, and then on a much larger scale on a monthly basis, which could result in a large amount of records that need to be updated in Salesforce.
Which strategy should the Solution Architect choose to handle this scenario?