Question 1

True or False: If you reduce your batch size, your overall efficiency will always increase.

Question 2

When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?

Question 3

Which of the following is NOT a flow metric?
(choose the best answer)

Question 4

What should the Developers do if, during the Sprint, the Product Owner asks them to add an urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work in Progress (WIP) Limits?
(choose the two best answers)

Question 5

A Service Level Expectation (SLE) forecast is a calculation about the future completion of an item that includes two things. What are those two things?
(Choose the best two answers)