In a meeting to discuss the minimum viable product (MVP) deployment of a new customer-facing application, the key stakeholder shares details of the application components and the application administrators share details of performance and integrity tests for the application.
The application will be made up of the following components:
A web server
- Steps to confirm the web server is operating correctly will take 15 minutes after the application server is online.
An application server
- Steps to confirm application server integrity will take 15 minutes after the database is online.
A database server
- The database server will be managed by a database administrator, with an agreed service-level agreement (SLA) to restore and validate database services within one hour.
The existing VMware infrastructure offers a recovery point objective (RPO) of 5 minutes and recovery time objective (RTO) of 15 minutes through a combination of backups and replication.
In the event of an outage impacting all three application components, how long will it take for the application to recover and complete all checks?
Following a company merger, there are two data centers running vSphere environments. Both data centers are leveraging separate Layer 3 vMotion networks.
Which requirement must be met in order to enable vMotion migration between these locations?
Which of the listed requirements would be classified as a recoverability non-functional requirement?
An architect is designing a new backup solution for a vSphere platform that has been recently upgraded to vSphere 7.
The architect wants the backup solution to perform the following:
Full virtual machine image backup and restore
Incremental virtual machine image backup and restore
File level backup and restore within both Windows and Linux virtual machines LAN-free backup Which functional requirement should the architect include in the design of the new backup solution?
An architect is designing an environment for a retail customer. The design will use a single small vCenter Server Appliance and a cluster of eight ESXi hosts at a remote site. There is a single 10 GbE connected network at the remote site to support all management services. It is not possible to create additional management networks at the remote site. Virtual machine backups at the site will be dependent on the vCenter Server being available.
Which design decision should the architect make to maximize availability for backups?