AgilePM-Practitioner Exam Question 36

(During the Foundations phase, Brinda Vyas organized a workshop that Hira facilitated. It was attended by Sukra Aroon, Mira, Lee Tan, and Developers from the two Delivery Teams. The goal was to define and align on what would be available for guests at the end of Project Increment 4.
Considering the workshop attendees, which of the following observations aligns with AgilePM?)
  • AgilePM-Practitioner Exam Question 37

    Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
  • AgilePM-Practitioner Exam Question 38

    How should the Project Manager encourage the contractors to turn up on time?
  • AgilePM-Practitioner Exam Question 39

    As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
    . Heavy rainfall affecting the Wellness Garden.
    . Local supplier issues causing material delivery delays.
    Dependency on external contractors for hydrotherapy equipment.
    The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
    In addition to the Developers, the teams include:

    (Sarah Lark is concerned that delays will mean lots of work but no measurable progress.
    Is it appropriate for Hira to change progress reports to focus on the Delivery Teams effort instead of delivered features?)
  • AgilePM-Practitioner Exam Question 40

    Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
    Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

    (Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)