AgilePM-Practitioner Exam Question 26
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations Department.
What action should the Project Manager take to resolve this?
' them and us ' culture between the Sales Department and the Operations Department.
What action should the Project Manager take to resolve this?
AgilePM-Practitioner Exam Question 27
Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(Stakeholders have shared concerns about tracking progress. Sarah Lark finds reports inadequate, and Lee Tan dislikes attending meetings.
Which 2 of the following actions would help the Delivery Teams to address these concerns?)
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(Stakeholders have shared concerns about tracking progress. Sarah Lark finds reports inadequate, and Lee Tan dislikes attending meetings.
Which 2 of the following actions would help the Delivery Teams to address these concerns?)
AgilePM-Practitioner Exam Question 28
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.

AgilePM-Practitioner Exam Question 29
For cognitive learning, which is the BEST example of providing ' learning feedback ' ?
AgilePM-Practitioner Exam Question 30
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Having provided some sample estimates for Hira to review, a number of stakeholders have challenged their accuracy-some suggesting that the work has been significantly over-estimated, while others believe it has been significantly under-estimated.
What should the Developers do?)

(Having provided some sample estimates for Hira to review, a number of stakeholders have challenged their accuracy-some suggesting that the work has been significantly over-estimated, while others believe it has been significantly under-estimated.
What should the Developers do?)