A project in schematic design with sustainability goals will soon begin a value engineering study. Which of the following would ensure that the value engineering study will not harm the project's sustainability?
Correct Answer: B
CMAA'sSustainability and Environmental Stewardshipguidance states that sustainable design objectives must befunctionally defined and integratedbefore performing value engineering (VE). Merely setting a certification level (LEED Silver or Platinum) does not ensure that sustainability objectives are protected during cost evaluation. The CMAA explains that: "During value engineering, sustainability goals should be documented as functional requirements so that proposed alternatives maintain environmental performance while achieving cost efficiency." Thus, optionB-establishing clear sustainability functional requirements-ensures that VE proposals respect the intended sustainability outcomes and do not degrade energy performance, materials reuse, or environmental targets. References (CMAA Documents): CMAA Construction Management Standards of Practice, Chapter 8 - Sustainability and Environmental Stewardship. CMAA CM Study Guide, Sustainability Domain, Objective 8.3: "Ensure sustainability requirements are maintained through design and value engineering."
Construction-Manager Exam Question 12
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?
Correct Answer: B
Under CMAA'sTime ManagementandRisk Managementdomains, when concurrent delays arise from different responsible parties (e.g. architect and contractor), the CM should perform aschedule impact analysisto apportion responsibility and guide mitigation. The CM should instruct both parties to mitigate their individual delays within their responsibilities. This approach helps the owner understand cost/time consequences, negotiate or handle claims, and manage risk. Option A is defeatist (accept delay without mitigation). Option C expects cost absorption by parties without analysis and may be unfair or contractually unsupported. Option D (liquidated damages) addresses contractor delay penalties but does not address architect-caused delay or concurrent delay complexities. The A-2 form is neutral; it does not automatically allow penalizing the contractor when both parties are at fault. The CM's best role is to analyze impacts and assist in allocation of responsibility-thus B is best.
Construction-Manager Exam Question 13
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?
Correct Answer: B
TheCMAA Cost Managementsection definesparametric estimatingas: "A method of estimating in which the cost of a project or component is determined by applying cost parameters (such as cost per square foot, cost per unit, or cost per linear foot) to known quantities or measurable project characteristics." This approach is typically used during early design stages when only limited design information is available but project parameters (e.g., size, type, location) are known. It provides a reliable and repeatable estimating method for benchmarking or budgeting. Conceptual estimatingrelies on very preliminary data or similar past projects, whilebottom-up estimating requires detailed quantity takeoffs and is used at later design stages.Analogous estimatinguses direct comparison with a completed project, not specific cost parameters. Hence, the correct answer isB. Parametric Estimating. References: CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Cost Management, Section: "Estimating Techniques." CMAA CM Study Guide, Cost Management Domain, Objective 4.2: "Apply parametric estimating techniques based on measurable parameters.
Construction-Manager Exam Question 14
It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the
Correct Answer: D
According to theCMAA Construction Management Standards of Practice, early involvement of the Construction Manager during thepre-design phaseprovides the greatest opportunity to influence project outcomes and mitigate risks. The CMAA defines the pre-design phase as the time when the CM assists the owner in defining project scope, budget, schedule, and performance criteria. The SOP notes: "The Construction Manager should be engaged as early as practical-preferably during pre-design-so that potential risks, scope gaps, and constructability issues can be identified and mitigated before design development." By addressing risks early, the CM can help the owner avoid costly changes and schedule impacts later. Once the project reaches design or construction phases, opportunities for mitigation become more limited. References (CMAA Documents): CMAA Construction Management Standards of Practice, Chapter 2 - Project Management, Section: "Pre- Design Phase." CMAA CM Study Guide, Project Management Domain, Objective 2.2: "Identify and mitigate potential project risks early."
Construction-Manager Exam Question 15
During the design phase, the CM should perform which of the following tasks?
Correct Answer: B
In theCMAA Project Managementchapter, during theDesign Phase, the CM's duties focus on evaluatingdesign progress, cost control, and schedule integration. The CMAA SOP specifies: "During the design phase, the Construction Manager should review design submissions for compliance with budget, schedule, and program requirements; participate in cost estimating and design coordination meetings; and support permitting and regulatory agency coordination." OptionBcorrectly reflects these core design-phase responsibilities: reviewing cost estimates, schematic design development, and attending scheduling or coordination conferences with agencies. The other options refer to administrative, construction-phase, or post-construction tasks, not design-phase CM functions. References: CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section: "Design Phase Services," pp. 23-26. CMAA Study Guide, Project Management Domain, Objective 2.3.