Construction-Manager Exam Question 21

A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner
  • Construction-Manager Exam Question 22

    A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?
  • Construction-Manager Exam Question 23

    The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
  • Construction-Manager Exam Question 24

    A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that
  • Construction-Manager Exam Question 25

    A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?