Construction-Manager Exam Question 26

The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non- conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?
  • Construction-Manager Exam Question 27

    The CM is tasked with analyzing the schedule variance of a project on a regular basis. The contractor's recent payment application includes a dramatic increase in earned hours than what was budgeted for the project. This MOST likely indicates
  • Construction-Manager Exam Question 28

    A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
    10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
    Which statement most accurately portrays program status?