PK0-004 Exam Question 46

A project team is showing off a new product prototype at a trade show, and potential customers are requesting more information.
Which of the following is the MOST efficient way to provide more information?
  • PK0-004 Exam Question 47

    One deliverable failed during testing, and this has already happened several times.
    Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
  • PK0-004 Exam Question 48

    A team member has reported Task 3 will be completed ahead of schedule.

    Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
  • PK0-004 Exam Question 49

    An active construction project must make immediate changes when it is discovered that the designated project area contains protected wetlands.
    Which of the following is the MOST likely impact to the project?
  • PK0-004 Exam Question 50

    During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because: