PK0-004 Exam Question 26
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?
Which of the following documents should the project manager create?
PK0-004 Exam Question 27
A Chief Executive Officer (CEO) has approached a project team member to request a project change.
Which of the following would be the BEST step for the project manager to take to prevent scope creep?
Which of the following would be the BEST step for the project manager to take to prevent scope creep?
PK0-004 Exam Question 28
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
* Project description
* Draft project timeline and schedule
* Rough milestones
* Draft project budget
* Draft resources required
* High-level risk review
Which of the following sections should be included in this document?
* Project description
* Draft project timeline and schedule
* Rough milestones
* Draft project budget
* Draft resources required
* High-level risk review
Which of the following sections should be included in this document?
PK0-004 Exam Question 29
In which of the following organizational structures would a project manager have the MOST authority?
PK0-004 Exam Question 30
Because of space limitations, there has been a long history of contention among the team.
Which of the following actions can the project manager take that would MOST contribute to a successful project?
Which of the following actions can the project manager take that would MOST contribute to a successful project?