PK0-004 Exam Question 31
During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship.
Which of the following should the project manager receive from the team members? (Select two.)
Which of the following should the project manager receive from the team members? (Select two.)
PK0-004 Exam Question 32
A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?
PK0-004 Exam Question 33
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
Which of the following steps should take place NEXT?
PK0-004 Exam Question 34
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
Which of the following is MOST likely to be the first document created by the project manager?
PK0-004 Exam Question 35
A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?
Which of the following is the MOST likely reason?