PK0-004 Exam Question 126
While planning a project, the project team estimates known expenses but also applies a margin of error for unknown expenses. Which of the following is the project team trying to determine?
PK0-004 Exam Question 127
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week Which of the following should the project manager do
NEXT?
NEXT?
PK0-004 Exam Question 128
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
PK0-004 Exam Question 129
An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?
PK0-004 Exam Question 130
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?