PK0-004 Exam Question 141
A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions. Which of the following strategies is the project manager applying?
PK0-004 Exam Question 142
The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:

Which of the following should be modified to BEST eliminate confusion?

Which of the following should be modified to BEST eliminate confusion?
PK0-004 Exam Question 143
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.
Which of the following should the project manager do to resolve this issue?
Which of the following should the project manager do to resolve this issue?
PK0-004 Exam Question 144
Which of the following documents ensures two parties do not share contractually binding information?
PK0-004 Exam Question 145
A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.
Which of the following is the BEST risk mitigation strategy that the project manager should use?
Which of the following is the BEST risk mitigation strategy that the project manager should use?