PK0-004 Exam Question 6
A project team is mainly based in a metropolitan are
a. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
a. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
PK0-004 Exam Question 7
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

Which of the following calculations accurately shows the critical path?

Which of the following calculations accurately shows the critical path?
PK0-004 Exam Question 8
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
This type of conflict resolution is known as:
PK0-004 Exam Question 9
Which of the following techniques modifies the schedule based upon resource constraints?
PK0-004 Exam Question 10
Which of the following activities are associated with the closing phase of a project? (Select
TWO)
TWO)