CCM Exam Question 21
Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
CCM Exam Question 22
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
CCM Exam Question 23
(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer's Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer's Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)
CCM Exam Question 24
(Which one of the following statements is correct regarding the Employer ' s Representative under the FIDIC Silver Book (edition 1999)?)
CCM Exam Question 25
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?