CCM Exam Question 36

Which of the following situations form legally binding contracts? (2 correct answers apply) Choose all of the correct answers (multiple possibilities)
  • CCM Exam Question 37

    You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
    2017), with Time for Completion of 5 months.
    The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
    1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
    The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
    What is the correct Commencement Date?
  • CCM Exam Question 38

    The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?
  • CCM Exam Question 39

    When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
    1999)?
  • CCM Exam Question 40

    Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?
    Choose all of the correct answers (multiple possibilities)