MB-320 Exam Question 96
You are the product design manager for a computer manufacturer.
Your new laptop model is configurable. There are restrictions on which hardware components can be selected depending on the model. You create configuration groups for hardware and software.
You need to create a new laptop item number and configurations.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Your new laptop model is configurable. There are restrictions on which hardware components can be selected depending on the model. You create configuration groups for hardware and software.
You need to create a new laptop item number and configurations.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 97
A company makes lubricants and greases used in the automotive industry. The company plans to implement Dynamics 365 for Finance and Operations. The system must meet the following requirements:
* Schedule the batch production of products.
* Plan for inventory fluctuations of ingredients that are used across different products.
* Schedule delivery of amounts of proprietary compounds used during production from vendors to keep production runs on schedule and eliminating excess stock on hand or delayed production.
The company is starting the initial setup of their Dynamics 365 environment.

* Schedule the batch production of products.
* Plan for inventory fluctuations of ingredients that are used across different products.
* Schedule delivery of amounts of proprietary compounds used during production from vendors to keep production runs on schedule and eliminating excess stock on hand or delayed production.
The company is starting the initial setup of their Dynamics 365 environment.

MB-320 Exam Question 98
You are a functional consultant for Contoso Entertainment System USA (USMF).
You need to configure the system to ensure that planned master orders generated by Material Requirements Planning (MRP) contain trade agreements.
To complete this task, sign in to Dynamics 365 portal.
You need to configure the system to ensure that planned master orders generated by Material Requirements Planning (MRP) contain trade agreements.
To complete this task, sign in to Dynamics 365 portal.
MB-320 Exam Question 99
A chemical manufacturing company uses Dynamics 365 Supply Chain Management. A batch of material has a quality issue and must be reworked.
You need to create the rework order the production.
Which three options must be set? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to create the rework order the production.
Which three options must be set? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
MB-320 Exam Question 100
A company uses Lean manufacturing concepts to produce paper plates redesigned the layout of the warehouse and production floor.
The company's production flow activities no longer match the tasks of the workers Employees use paper and manual communication to complete the tasks.
You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

The company's production flow activities no longer match the tasks of the workers Employees use paper and manual communication to complete the tasks.
You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.