MB-320 Exam Question 76
A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
MB-320 Exam Question 77
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:
* The setup uses a Lean schedule group with a throughput ratio = 2.
* The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
* The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
* The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item's production flow activity.
* The setup uses a Lean schedule group with a throughput ratio = 2.
* The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
* The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
* The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item's production flow activity.
MB-320 Exam Question 78
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
* Edit the existing production flow and set the expiration date to the end of the month.
* Using the existing production flow, create a production flow and version. Set the expiration date to the end of the month. Create an activity for the new process step and add it in the proper sequence.
* Create a Kanban rule that uses the last day of the month as the effective date.
* Edit the existing Kanban rule. Set the expiration date to the end of the month. Set the new Kanban rule as the replacement Kanban rule.
* Activate the new production flow.
Does the solution meet the goal?
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
* Edit the existing production flow and set the expiration date to the end of the month.
* Using the existing production flow, create a production flow and version. Set the expiration date to the end of the month. Create an activity for the new process step and add it in the proper sequence.
* Create a Kanban rule that uses the last day of the month as the effective date.
* Edit the existing Kanban rule. Set the expiration date to the end of the month. Set the new Kanban rule as the replacement Kanban rule.
* Activate the new production flow.
Does the solution meet the goal?
MB-320 Exam Question 79
A company implements Dynamics 365 for Finance and Operations.
Production orders are generated for products directly from projects. You create the following production order:

Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is worth one point.

Production orders are generated for products directly from projects. You create the following production order:

Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is worth one point.

MB-320 Exam Question 80
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
1.) Create an activity for the new process step and add it to the existing production flow. Set the expiration date to the end of the month
2.) Create a Kanban rule that incorporates the new activity with an effective date of end of the month
3.) Edit the existing Kanban rule. Set the expiration date to the end of the month.
4.) Activate the new production flow
Does the solution meet the goal?
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
1.) Create an activity for the new process step and add it to the existing production flow. Set the expiration date to the end of the month
2.) Create a Kanban rule that incorporates the new activity with an effective date of end of the month
3.) Edit the existing Kanban rule. Set the expiration date to the end of the month.
4.) Activate the new production flow
Does the solution meet the goal?