PVIP Exam Question 46
A PV module is mounted with a 2-inch standoff from a shingle roof. What is the minimum clearance required for fire access per the International Fire Code (IFC)?
PVIP Exam Question 47
A PV system has a nameplate capacity of 10 kW DC and operates with a total system derate factor of 0.85.
What is the expected AC output power under standard test conditions (STC)?
What is the expected AC output power under standard test conditions (STC)?
PVIP Exam Question 48
When doing initial inspections on a PV system that was installed using racking that is not compliant with UL.
2703, an inspector should pay special attention to which electrical attribute?
2703, an inspector should pay special attention to which electrical attribute?
PVIP Exam Question 49
A PV array is installed with a rapid shutdown system per NEC 690.12. The array is 15 feet from the service entrance. What is the maximum voltage allowed within the array boundary 30 seconds after shutdown initiation?
PVIP Exam Question 50
An installer is using ½ in lag boits to secure roof-monitoring hardware to rafters through a roof deck. Which of the following should the installer predrill?