NCS-Core Exam Question 96
Refer to the exhibit.

A Nutanix host is connected as shown in the exhibit with br0-up set to active/backup. Physical Switch 1 experiences a power outage causing br0-up to failover to using eth2. The CVM and host become inaccessible.
User VMs restart on other hosts in the cluster, which causes a disruption to those VMs.
Which configuration issue likely caused this outage?

A Nutanix host is connected as shown in the exhibit with br0-up set to active/backup. Physical Switch 1 experiences a power outage causing br0-up to failover to using eth2. The CVM and host become inaccessible.
User VMs restart on other hosts in the cluster, which causes a disruption to those VMs.
Which configuration issue likely caused this outage?
NCS-Core Exam Question 97
At which prompt should a consultant execute the command nanage_ovs -bridge_nawe brO show_uplinks in a Nutanix cluster?
NCS-Core Exam Question 98
During a pre-engagement call, a customer explains that network cables are missing from the boxes. The consultant examines the bill of materials more closely to verify the quantity and type required by the hardware.
The rack is already equipped with one OOBM Ethernet switch and two 10GbE SFP+ ToR switches.

Which cables should the consultant recommend to the customer for implementing in this scenario?
The rack is already equipped with one OOBM Ethernet switch and two 10GbE SFP+ ToR switches.

Which cables should the consultant recommend to the customer for implementing in this scenario?
NCS-Core Exam Question 99
A consultant successfully installs the Foundation VM on a laptop and needs to ensure the VM can communicate externally.
Which two configuration changes should the consultant make next? (Choose two.)
Which two configuration changes should the consultant make next? (Choose two.)
NCS-Core Exam Question 100
An administrator needs to migrate workloads from a Nutanix cluster running VMware ESXi to Nutanix AHV.
The migration process needs to be completed in multiple VM groups and support roll back in case any problems are found during user acceptance testing.
Which action should the administrator perform?
The migration process needs to be completed in multiple VM groups and support roll back in case any problems are found during user acceptance testing.
Which action should the administrator perform?