NCS-Core Exam Question 131
During a technical call with a customer, it is identified that this installation will be software only on Dell servers. The out-of-band management interfaces will not be given IP addresses until the consultant is onsite.
Which Foundation method should be used for this type of installation?
Which Foundation method should be used for this type of installation?
NCS-Core Exam Question 132
A customer has a primary datacenter with 12 Nutanix blocks distributed across three racks. The customer wants toachieve the most resiliency possible. They also have a datacenter in a branch office that is 400 kilometers away from the primary datacenter.
Which two solutions should be used? (Choose two.)
Which two solutions should be used? (Choose two.)
NCS-Core Exam Question 133
Which Nutanix feature creation is described in the Knowledge Transfer?
NCS-Core Exam Question 134
A customer has provided the following network requirements to their consultant during a discovery session for AHV cluster deployments:
*Maximum Uptime Guest Traffic is a Hard Requirement
*Maximum Throughput for Guest is a Hard Requirement
*Link Aggregation is established at the TORs
Cluster nodes have the following network card configurations:
*2 x 40GbE Adapters
*2 x IGbE Adapters
How should the consultant satisfy these requirements?
*Maximum Uptime Guest Traffic is a Hard Requirement
*Maximum Throughput for Guest is a Hard Requirement
*Link Aggregation is established at the TORs
Cluster nodes have the following network card configurations:
*2 x 40GbE Adapters
*2 x IGbE Adapters
How should the consultant satisfy these requirements?
NCS-Core Exam Question 135
Refer to Exhibit:

A customer is preparing to expand a cluster with a consultant. The production cluster is comprised of one NX-3460-G7 and two NX-8235 G8 blocks. The running AOS version is 5.20.4.6 and Hypervisor version is ESXi 6.7 U3b. vCenter is also running a 6.7 version.
One NX-3235-G9 block will be added to that cluster (ESXI-NUTA-09 and ESXI-NUTA-10).
The consultant has verified Nutanix documentation and customer's As-Built guide:
*NX-3060-G7 and NX-8035-G8 are hybrid HCI nodes
*ESXi 6.7 U3b is unsupported for the new G9 hardware model
*AOS 5.20.X and ESXi 6 X are end of support
*NX-3060-G7 and NX-8035-G8 hypervisors can be upgraded to the latest ESXi supported version What actions should be taken before beginning the cluster expansion?

A customer is preparing to expand a cluster with a consultant. The production cluster is comprised of one NX-3460-G7 and two NX-8235 G8 blocks. The running AOS version is 5.20.4.6 and Hypervisor version is ESXi 6.7 U3b. vCenter is also running a 6.7 version.
One NX-3235-G9 block will be added to that cluster (ESXI-NUTA-09 and ESXI-NUTA-10).
The consultant has verified Nutanix documentation and customer's As-Built guide:
*NX-3060-G7 and NX-8035-G8 are hybrid HCI nodes
*ESXi 6.7 U3b is unsupported for the new G9 hardware model
*AOS 5.20.X and ESXi 6 X are end of support
*NX-3060-G7 and NX-8035-G8 hypervisors can be upgraded to the latest ESXi supported version What actions should be taken before beginning the cluster expansion?