CAPM Exam Question 346
Which tool or technique is used in the Develop Project Management Plan process?
Correct Answer: D
According to the PMBOKGuide and the Standard for Project Management, specifically within the Project Integration Management Knowledge Area, Expert Judgment is a primary tool and technique used in the Develop Project Management Plan process.
As per PMI standards, Develop Project Management Plan is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan. Expert Judgment is defined as judgment provided based upon expertise in an application area, Knowledge Area, discipline, industry, etc., as appropriate for the activity being performed. In this specific process, expert judgment is used to:
Tailor the Process: Determine which processes from the PMBOKGuide are appropriate for the specific project.
* Develop Technical Details: Provide expertise on the technical and management details to be included in the plan.
* Determine Resources: Assist in determining the resources and skill levels needed to perform project work.
* Define Management Levels: Establish the level of configuration management and change control to be applied to the project.
The other options are incorrect based on their specific placement within the PMI framework:
Pareto diagram: This is a Quality Management tool (a vertical bar chart) used in the Manage Quality and Control Quality processes to identify the vital few sources that are responsible for causing the most causes of effects.
* Performance reporting: This is part of the Monitor and Control Project Work and Manage Communications processes. It involves collecting and distributing performance information, including status reports and progress measurements, rather than planning how the project will be managed.
* SWOT analysis: As seen in previous questions, this is a tool used in the Identify Risks process to identify strengths, weaknesses, opportunities, and threats.
* Expert Judgment is also used in many other processes (like Develop Project Charter or Define Scope), but among the choices provided, it is the only one listed as an official tool/technique for the Develop Project Management Plan process.
As per the PMI Lexicon of Project Management Terms, Expert Judgment ensures that the Project Management Plan is realistic, comprehensive, and based on proven organizational or industry practices.
As per PMI standards, Develop Project Management Plan is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan. Expert Judgment is defined as judgment provided based upon expertise in an application area, Knowledge Area, discipline, industry, etc., as appropriate for the activity being performed. In this specific process, expert judgment is used to:
Tailor the Process: Determine which processes from the PMBOKGuide are appropriate for the specific project.
* Develop Technical Details: Provide expertise on the technical and management details to be included in the plan.
* Determine Resources: Assist in determining the resources and skill levels needed to perform project work.
* Define Management Levels: Establish the level of configuration management and change control to be applied to the project.
The other options are incorrect based on their specific placement within the PMI framework:
Pareto diagram: This is a Quality Management tool (a vertical bar chart) used in the Manage Quality and Control Quality processes to identify the vital few sources that are responsible for causing the most causes of effects.
* Performance reporting: This is part of the Monitor and Control Project Work and Manage Communications processes. It involves collecting and distributing performance information, including status reports and progress measurements, rather than planning how the project will be managed.
* SWOT analysis: As seen in previous questions, this is a tool used in the Identify Risks process to identify strengths, weaknesses, opportunities, and threats.
* Expert Judgment is also used in many other processes (like Develop Project Charter or Define Scope), but among the choices provided, it is the only one listed as an official tool/technique for the Develop Project Management Plan process.
As per the PMI Lexicon of Project Management Terms, Expert Judgment ensures that the Project Management Plan is realistic, comprehensive, and based on proven organizational or industry practices.
CAPM Exam Question 347
Which is an example of Administer Procurements?
Correct Answer: B
According to the PMBOK Guide, the process referred to as Administer Procurements (now commonly termed Control Procurements in the most recent editions) is the process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts.
* Authorizing Contractor Work: This is a core function of contract administration. It involves ensuring that the seller ' s work is started at the appropriate time as defined by the project schedule and contract terms. This often involves a work authorization system to ensure that work is done by the right organization, at the right time, and in the right proper sequence.
* Key Activities in this Process:
* Performance Reporting: Evaluating the seller ' s performance to ensure they are meeting contractual obligations.
* Payment Systems: Processing invoices and making payments to the contractor.
* Change Control: Managing any requested changes to the contract or the scope of work provided by the seller.
* Inspections and Audits: Verifying that the contractor ' s deliverables meet the required quality standards.
* The Goal: The primary focus is ensuring that both the buyer and the seller meet their respective contractual obligations.
Comparison with other options:
* A. Negotiating the contract: This is a tool and technique used in the Conduct Procurements process (Executing phase), which occurs before a contract is signed and administered.
* C. Developing the statement of work: This is an activity performed during the Plan Procurement Management process (Planning phase) to define the portion of the project scope to be included within the related contract.
* D. Establishing evaluation criteria: This is also part of the Plan Procurement Management process.
These criteria are used later to rate or score seller proposals during the Conduct Procurements process.
* Authorizing Contractor Work: This is a core function of contract administration. It involves ensuring that the seller ' s work is started at the appropriate time as defined by the project schedule and contract terms. This often involves a work authorization system to ensure that work is done by the right organization, at the right time, and in the right proper sequence.
* Key Activities in this Process:
* Performance Reporting: Evaluating the seller ' s performance to ensure they are meeting contractual obligations.
* Payment Systems: Processing invoices and making payments to the contractor.
* Change Control: Managing any requested changes to the contract or the scope of work provided by the seller.
* Inspections and Audits: Verifying that the contractor ' s deliverables meet the required quality standards.
* The Goal: The primary focus is ensuring that both the buyer and the seller meet their respective contractual obligations.
Comparison with other options:
* A. Negotiating the contract: This is a tool and technique used in the Conduct Procurements process (Executing phase), which occurs before a contract is signed and administered.
* C. Developing the statement of work: This is an activity performed during the Plan Procurement Management process (Planning phase) to define the portion of the project scope to be included within the related contract.
* D. Establishing evaluation criteria: This is also part of the Plan Procurement Management process.
These criteria are used later to rate or score seller proposals during the Conduct Procurements process.
CAPM Exam Question 348
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Correct Answer: A
According to the PMBOK Guide, specifically within the Sequence Activities process of Project Schedule Management, there are four types of dependencies used to define the logical relationship between activities.
* Mandatory Dependencies: These are also known as " hard logic " or " hard dependencies. " They are legally or contractually required or inherent in the nature of the work. These dependencies often involve physical limitations. For example, on a construction project, you cannot build the walls until the foundation is poured and set. This is a physical requirement of the work itself.
* Attributes: Mandatory dependencies are typically fixed and cannot be easily changed by the project team without changing the fundamental nature of the project or violating legal/safety standards.
Why the other options are incorrect:
* B. Discretionary: Also known as " preferred logic, " " soft logic, " or " preferential logic. " These are based on best practices or specific sequences desired by the team even though other sequences are possible. They are not legally or physically required.
* C. Internal: These involve a precedence relationship between project activities and are generally within the project team's control. While a dependency can be both mandatory and internal, the question ' s specific definition of " legally/contractually required " points directly to the classification of Mandatory.
* D. External: These involve a relationship between project activities and non-project activities (e.g., waiting for a government permit or a delivery from a vendor). While these can be mandatory, the primary definition of work inherent to the nature of the task and physical limitations is the hallmark of a Mandatory dependency.
* Mandatory Dependencies: These are also known as " hard logic " or " hard dependencies. " They are legally or contractually required or inherent in the nature of the work. These dependencies often involve physical limitations. For example, on a construction project, you cannot build the walls until the foundation is poured and set. This is a physical requirement of the work itself.
* Attributes: Mandatory dependencies are typically fixed and cannot be easily changed by the project team without changing the fundamental nature of the project or violating legal/safety standards.
Why the other options are incorrect:
* B. Discretionary: Also known as " preferred logic, " " soft logic, " or " preferential logic. " These are based on best practices or specific sequences desired by the team even though other sequences are possible. They are not legally or physically required.
* C. Internal: These involve a precedence relationship between project activities and are generally within the project team's control. While a dependency can be both mandatory and internal, the question ' s specific definition of " legally/contractually required " points directly to the classification of Mandatory.
* D. External: These involve a relationship between project activities and non-project activities (e.g., waiting for a government permit or a delivery from a vendor). While these can be mandatory, the primary definition of work inherent to the nature of the task and physical limitations is the hallmark of a Mandatory dependency.
CAPM Exam Question 349
Which process determines the risks that might affect the project?
Correct Answer: B
According to the PMBOK Guide and the Practice Standard for Project Risk Management, the process specifically designed to determine which risks may affect the project and to document their characteristics is Identify Risks.
* Objective: The primary goal of this process is to uncover both individual project risks and sources of overall project risk. It is an iterative process because new risks may evolve or become known as the project progresses through its life cycle.
* Documentation: The key output of this process is the Risk Register, which initially captures the list of identified risks, potential risk owners, and a list of potential risk responses. It also results in updates to the Risk Report.
* Tools and Techniques: To determine these risks, project managers use techniques such as:
* Brainstorming and Checklists.
* SWOT Analysis (Strengths, Weaknesses, Opportunities, and Threats).
* Prompt Lists (e.g., PESTLE, TECOP).
* Root Cause Analysis.
* Comparison with Other Options:
* Plan Risk Management (C): This process defines how to conduct risk management activities; it does not identify the specific risks themselves.
* Perform Qualitative Risk Analysis (A): This process takes the risks already identified and prioritizes them by assessing their probability and impact.
* Perform Quantitative Risk Analysis (D): This process numerically analyzes the combined effect of identified individual project risks on overall project objectives.
* Objective: The primary goal of this process is to uncover both individual project risks and sources of overall project risk. It is an iterative process because new risks may evolve or become known as the project progresses through its life cycle.
* Documentation: The key output of this process is the Risk Register, which initially captures the list of identified risks, potential risk owners, and a list of potential risk responses. It also results in updates to the Risk Report.
* Tools and Techniques: To determine these risks, project managers use techniques such as:
* Brainstorming and Checklists.
* SWOT Analysis (Strengths, Weaknesses, Opportunities, and Threats).
* Prompt Lists (e.g., PESTLE, TECOP).
* Root Cause Analysis.
* Comparison with Other Options:
* Plan Risk Management (C): This process defines how to conduct risk management activities; it does not identify the specific risks themselves.
* Perform Qualitative Risk Analysis (A): This process takes the risks already identified and prioritizes them by assessing their probability and impact.
* Perform Quantitative Risk Analysis (D): This process numerically analyzes the combined effect of identified individual project risks on overall project objectives.
CAPM Exam Question 350
Which tool or technique is used in the Perform Integrated Change Control process?
Correct Answer: D
In accordance with the PMBOKGuide (Project Integration Management), the Perform Integrated Change Control process is the process of reviewing all change requests; approving changes and managing changes to deliverables, project documents, and the project management plan; and communicating the decisions.
Meetings are a primary tool and technique specifically used for this process, often referred to as Change Control Board (CCB) meetings.
* Role of the CCB: The Change Control Board is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project.
* Meeting Function: During these meetings, the impact of each change request is discussed. The board reviews the configuration management activities and determines the feasibility of the change in relation to the project ' s scope, schedule, cost, and risk baselines.
* Decision Documentation: The outcome of these meetings is recorded in the Change Log as approved or rejected change requests.
* Other Tools and Techniques: This process also utilizes Expert Judgment, Change Control Tools (manual or automated), and Data Analysis (including Alternatives Analysis and Cost-Benefit Analysis).
Analysis of Distractors:
* A. Decomposition: This is a tool and technique used in Create WBS and Define Activities. It involves breaking down project scope and deliverables into smaller, more manageable components.
* B. Modeling techniques: These are typically used in Develop Schedule (e.g., Schedule Network Analysis or S Curve) or Estimate Costs to simulate different scenarios.
* C. Resource optimization: This is a tool and technique used in Develop Schedule and Control Schedule (such as Resource Leveling or Resource Smoothing) to adjust the schedule model based on resource demand and supply.
Meetings are a primary tool and technique specifically used for this process, often referred to as Change Control Board (CCB) meetings.
* Role of the CCB: The Change Control Board is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project.
* Meeting Function: During these meetings, the impact of each change request is discussed. The board reviews the configuration management activities and determines the feasibility of the change in relation to the project ' s scope, schedule, cost, and risk baselines.
* Decision Documentation: The outcome of these meetings is recorded in the Change Log as approved or rejected change requests.
* Other Tools and Techniques: This process also utilizes Expert Judgment, Change Control Tools (manual or automated), and Data Analysis (including Alternatives Analysis and Cost-Benefit Analysis).
Analysis of Distractors:
* A. Decomposition: This is a tool and technique used in Create WBS and Define Activities. It involves breaking down project scope and deliverables into smaller, more manageable components.
* B. Modeling techniques: These are typically used in Develop Schedule (e.g., Schedule Network Analysis or S Curve) or Estimate Costs to simulate different scenarios.
* C. Resource optimization: This is a tool and technique used in Develop Schedule and Control Schedule (such as Resource Leveling or Resource Smoothing) to adjust the schedule model based on resource demand and supply.
- Other Version
- 2879PMI.CAPM.v2026-09-05.q632
- 4946PMI.CAPM.v2026-07-17.q643
- 5552PMI.CAPM.v2023-02-14.q281
- 12161PMI.CAPM.v2022-05-24.q570
- 59PMI.Pass4guide.CAPM.v2022-05-12.by.shirley.570q.pdf
- 15036PMI.CAPM.v2022-01-02.q768
- 89PMI.Exams4sures.CAPM.v2021-08-25.by.odelette.722q.pdf
- Latest Upload
- 161Oracle.1Z0-931-26.v2026-10-19.q61
- 157Microsoft.AI-200.v2026-10-19.q43
- 133Oracle.1z0-1195-26.v2026-10-19.q23
- 235Microsoft.MS-102.v2026-10-19.q259
- 219ECCouncil.312-50v13.v2026-10-19.q453
- 201Oracle.1Z0-1110-26.v2026-10-17.q71
- 265CloudSecurityAlliance.CCSK.v2026-10-17.q153
- 298Salesforce.Platform-App-Builder.v2026-10-17.q161
- 178Salesforce.AP-204.v2026-10-17.q40
- 277Microsoft.AI-103.v2026-10-16.q46