PMI-RMP Exam Question 41

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
  • PMI-RMP Exam Question 42

    In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
    In implementing this plan, which response should the risk manager use?
  • PMI-RMP Exam Question 43

    in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
    Which tool could the risk manager use to discover the project risk categories?
  • PMI-RMP Exam Question 44

    The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.
    How should project X's project manager avoid this situation in the future?
  • PMI-RMP Exam Question 45

    A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
    What should the risk management professional do next?