PMI-RMP Exam Question 61

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?
  • PMI-RMP Exam Question 62

    A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.
    Which analytical tool should the risk manager use?
  • PMI-RMP Exam Question 63

    While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
    What should the project manager do next?
  • PMI-RMP Exam Question 64

    A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?
  • PMI-RMP Exam Question 65

    A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
    What type of risk is being referred to here?