PMI-RMP Exam Question 56
The scope of a large mobile network deployment project includes equipment to be furnished by the customer.
The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?
The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.
What should the risk manager do?
PMI-RMP Exam Question 57
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?
PMI-RMP Exam Question 58
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
What two actions should the risk manager do next? (Choose two.)
PMI-RMP Exam Question 59
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
How should the project manager handle stakeholder expectations?
PMI-RMP Exam Question 60
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
What should the project manager do next to avoid similar risks?