PMI-RMP Exam Question 1

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
  • PMI-RMP Exam Question 2

    A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
    What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
  • PMI-RMP Exam Question 3

    A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.
    How should the risk manager address this concern?
  • PMI-RMP Exam Question 4

    During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.
    What should the risk manager do?
  • PMI-RMP Exam Question 5

    Which statement describes the risk portrayed on the risk matrix heat map below?