PMI-RMP Exam Question 11

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
  • PMI-RMP Exam Question 12

    An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
  • PMI-RMP Exam Question 13

    A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.
    What should the risk manager do?
  • PMI-RMP Exam Question 14

    Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
    What will help calculate the impact?
  • PMI-RMP Exam Question 15

    One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
    Which risk response strategy is the program manager using in this scenario?