PMP Exam Question 566

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?
  • PMP Exam Question 567

    The nature of project work is such that it inevitably causes stress. Project managers thus need to learn how to cope with and manage stress and understand what stress is and why it is created. Project managers need to note that it can be a positive experience depending on how people perceive stress and should work to mentor team members accordingly. As you strive to become more aware of stress, which one of the following is NOT considered a stress-creating factor that is related to the project environment?
  • PMP Exam Question 568

    A project manager receives project charier approval for an expansion project Subsequently the government introduces a new regulation with which the expansion project must comply This will significantly impact the project's schedule and budget What should the project manager do?
  • PMP Exam Question 569

    Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
  • PMP Exam Question 570

    Project deliverables that have been completed and checked for correctness through the Control Quality process are known as: