You are responsible for preparing a cost estimate for a large World Bank project. You decide to prepare a bottom-up estimate because your estimate needs to be as accurate as possible. Your first step is to______________
Correct Answer: C
Explanation/Reference: Explanation: Bottom-up estimating is derived by first estimating the cost of the project's elemental tasks at the lower levels of the WBS or for an activity and then aggregating those estimates at successively higher levels of the WBS for subsequent reporting and tracking purposes.