PMP Exam Question 636
Which of the following techniques uses a weighted average duration estimate to calculate activity durations?
PMP Exam Question 637
You work for a telecommunications company, and when developing a project management plan for a new project, you found that you must tailor some company processes because the product is so different than those products typically produced by your company. To tailor these processes, you will follow______________.
PMP Exam Question 638
A project manager is creating a program evaluation and review technique (PERT) diagram. A primary activity on the critical path has a most optimistic time of three weeks, a most pessimistic time of seven weeks, and a most likely time of five weeks.
What is the activity's expected time?
What is the activity's expected time?
PMP Exam Question 639
Decomposition is a technique used to break larger, complex items into smaller and more manageable items. Which following statement best describes the role decomposition plays in creating the WBS?
PMP Exam Question 640
The project manager of a large software implementation project is preparing for a kick-off meeting. While reviewing all available project information, the project manager discovers that the project's key deliverables are not clearly identified.
What should the project manager do?
What should the project manager do?