PMP Exam Question 26

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?
  • PMP Exam Question 27

    You are project manager for a systems integration effort and need to procure the hardware components from external sources. Your subcontracts administrator has told you to prepare a product description, which is referenced in a______________.
  • PMP Exam Question 28

    Which of the following are not tools/ techniques that can be used to create the WBS?
  • PMP Exam Question 29

    Your customer signed off on the requirements document and scope statement of your video game project last month. Today she stated she would like to make it an interactive game that can be played on a television and on a computer. This represents a requested scope change that, at a minimum______________
  • PMP Exam Question 30

    A project manager joins a project to handle the merger between a digital marketing firm and an advertising firm. Team members from both firms are finding it difficult to work together. What should the project manager do?