PMP Exam Question 51

A new project manager joins a project in progress. The project manager is unclear about what environmental factors may impact effective information reporting to key stakeholders.
What should the project manager reference to understand these impacts?
  • PMP Exam Question 52

    A supplier informs the project team that they can proceed with an option to add a functionality to a product.
    The functionality was listed as an optional requirement
    delivery in the project charter, with no impact on cost or schedule.
    What should the project manager do?
  • PMP Exam Question 53

    Market conditions and published commercial information are examples of which input to the Estimate Costs process?
  • PMP Exam Question 54

    A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
  • PMP Exam Question 55

    Requirements for formal deliverable acceptance are defined in the______________