PMP Exam Question 766
The Project Manager is in the process of planning the project. The company he works for has had issues with previous projects in which there has been confusion over who is accountable for completion of various activities and processes associated with the projects. What document can he include in the project management plan that will help eliminate this problem?
PMP Exam Question 767
You are a Project Manager managing the building of a housing development. As the plumbing is being installed, you cannot find a building permit. As the Project Manager, to whom do you report this violation?
PMP Exam Question 768
A change has occurred on your project. You've documented the change, filled out a change request, and submitted that request to the change control board (CCB). What's the NEXT thing that must happen on the project?
PMP Exam Question 769
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
PMP Exam Question 770
Which of the following is an input to the Develop Project Charter process?