PMP Exam Question 771

Contested changes are requested changes when the buyer and seller cannot agree on compensation for the change. They are also known as all but which one of the following?
  • PMP Exam Question 772

    In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Complete for your project?
    BAC = $ 300,000 AC = $ 100,000 EV = $ 150,000 CPI = $ 1.2 ETC = $ 120,000
  • PMP Exam Question 773

    In the Define Activities process, the schedule management plan is used to:
  • PMP Exam Question 774

    Which quality management tool would be used to determine potential causes of a production problem?
  • PMP Exam Question 775

    On your systems development project, you noted during a review that the system had less functionality than planned at the critical design review. This note suggests that during the control risks process you used which following tools and techniques?