PMP Exam Question 771
Contested changes are requested changes when the buyer and seller cannot agree on compensation for the change. They are also known as all but which one of the following?
PMP Exam Question 772
In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Complete for your project?
BAC = $ 300,000 AC = $ 100,000 EV = $ 150,000 CPI = $ 1.2 ETC = $ 120,000
BAC = $ 300,000 AC = $ 100,000 EV = $ 150,000 CPI = $ 1.2 ETC = $ 120,000
PMP Exam Question 773
In the Define Activities process, the schedule management plan is used to:
PMP Exam Question 774
Which quality management tool would be used to determine potential causes of a production problem?
PMP Exam Question 775
On your systems development project, you noted during a review that the system had less functionality than planned at the critical design review. This note suggests that during the control risks process you used which following tools and techniques?