PMP Exam Question 231

All of the following are true regarding the Quality Planning process except for which one?
  • PMP Exam Question 232

    If the probability of event 1 is 80 percent and of event 2 is 70 percent and they are independent events, how likely is it that both events will occur?
  • PMP Exam Question 233

    A key stakeholder is concerned about a critical risk that may cause the project to run over budget. The project manager wants to share the mitigation plan with the stakeholder.
    What should the project manager do first?
  • PMP Exam Question 234

    Which of the following best describes risks that arise as a direct implementation of implementing a risk response?
  • PMP Exam Question 235

    An input of the Create WBS process is: