PMP Exam Question 156
During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style What should the project manager do?
PMP Exam Question 157
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members.
When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan What should the project manager do?
When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan What should the project manager do?
PMP Exam Question 158
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
What should the project manager do next?
PMP Exam Question 159
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
PMP Exam Question 160
A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it.
What should the project manager do?
What should the project manager do?