PMP Exam Question 131
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product After collecting the new requirements, what should the project manager do?
PMP Exam Question 132
A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years' experience as an agile practitioner working as a scrum master.
What should the project manager do at the start of the project?
What should the project manager do at the start of the project?
PMP Exam Question 133
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
What role does the project manager play in this situation?
PMP Exam Question 134
In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.
What should the project manager do?
What should the project manager do?
PMP Exam Question 135
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in one of the project teams.
What should the project manager do?
What should the project manager do?