PMP Exam Question 81

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of the components is poor and is concerned that, as a result, their products will be returned due to quality issues.
The project manager is certain that
quality has been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?
  • PMP Exam Question 82

    A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts with the other team members. As a result, the other team members are refusing to work with the developer.
    Since the developer is a high
    performer, the project goals may be negatively impacted if they leave the team.
    What should the project manager do in this situation?
  • PMP Exam Question 83

    During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
    Which of the documents was likely missed or outdated?
  • PMP Exam Question 84

    A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
    What should the project manager do?
  • PMP Exam Question 85

    A team realizes that there is no access to data that the project depends on to complete the current iteration.
    This
    dependency was known; however, the team is unsure of the available options to remove this obstacle.
    What should the project manager do next?