PMP Exam Question 91

Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting.
What should the project manager do?
  • PMP Exam Question 92

    Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
  • PMP Exam Question 93

    Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.
    What should the project manager do?
  • PMP Exam Question 94

    While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?
  • PMP Exam Question 95

    A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks Drag each risk type on the left to its correct example on the right