PMP Exam Question 141
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months.
What should the project manager do to align stakeholders' needs and expectations?
What should the project manager do to align stakeholders' needs and expectations?
PMP Exam Question 142
A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?
PMP Exam Question 143
A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.
What should the project manager do first?
What should the project manager do first?
PMP Exam Question 144
A project manager is leading a hybrid project funded by a time and materials (T&M) agreement. The project was completed, and the client accepted the delivery of the product. One week later, the client asked the project manager to fix two defects they found in the product. The project manager responded with an estimate of time and money and asked the client to confirm this. The client disagreed and insisted that the work should be done for free because it is a defect in the product.
What should the project manager have done to prevent this?
What should the project manager have done to prevent this?
PMP Exam Question 145
A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog.
At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?