PMP Exam Question 176

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4 months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the following resources:
* Two engineers (monthly salary of US$700 each)
* One project manager (monthly salary of US$1,600)
* Additional estimated monthly expenses of US$2,000
The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house resources.
How much money will the project manager estimate the company can save?
  • PMP Exam Question 177

    An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.
    What should the project manager do to help the project team?
  • PMP Exam Question 178

    A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users.
    What should the project manager do?
  • PMP Exam Question 179

    A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.
    What should the project manager do first?
  • PMP Exam Question 180

    A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?