PMP Exam Question 371

The purpose of a numeric scale in risk management is to______________
  • PMP Exam Question 372

    The most important criteria in selecting project selection method is:
  • PMP Exam Question 373

    A project manager has been assigned to an important project that will help set the future of the company.
    Meanwhile, the project management office (PMO) is implementing
    adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
    What should the project manager do?
  • PMP Exam Question 374

    During a documentation audit of an international company, it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.
    How should the project manager have handled documentation for the project?
  • PMP Exam Question 375

    After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.
    What should the project manager do?