PMP Exam Question 391

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.
What should the project manager do?
  • PMP Exam Question 392

    You are the Chief Technology Officer of a major stock exchange. You are in the charge of the project to reengineer the organization's back office accounting, billing and administrative system. Your project team is in the process of implementing the technical work required for the
    project. However one of the stakeholders for your project is requesting variance changes to the project. Which of the following is the best approach to take the beginning of the project in order to manage the project?
  • PMP Exam Question 393

    Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

    PMP Exam Question 394

    A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy.
    What should the project manager do first to address this situation?
  • PMP Exam Question 395

    A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.
    What should the project manager have done to prevent this situation?