PMP Exam Question 71

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.
What should the project manager do to mitigate this risk?
  • PMP Exam Question 72

    A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
    How should the project manager ensure that project risks are reported accurately in the risk register?
  • PMP Exam Question 73

    A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed- price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.
    What should the project manager do?
  • PMP Exam Question 74

    During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
  • PMP Exam Question 75

    A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.
    What should the project manager do next?