PMP Exam Question 81
A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.
What should the project manager do?
What should the project manager do?
PMP Exam Question 82
A company is working on a project and is using a hybrid approach to streamline a customer service process.
At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
PMP Exam Question 83
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.
How should the project manager improve this situation with the project team?
How should the project manager improve this situation with the project team?
PMP Exam Question 84
A supplier was supposed to mobilize a government-issued, licensed piece of equipment two days ago, but did not. The procurement manager was informed that the supplier failed to check the validity of the license, which expired last week. The supplier had already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.
Which action should the project manager take?
Which action should the project manager take?
PMP Exam Question 85
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?