PMP Exam Question 321

The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.
What should the scrum master do first?
  • PMP Exam Question 322

    A project team is executing a project to replace an existing system with a new one.
    A new project manager has been hired and observes that the team consist of professionals who have worked with the older system, and others who have little previous experience.
    What should the project manager do to ensure project success?
  • PMP Exam Question 323

    The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project How should the project manager alert the new project sponsor about these concerns?
  • PMP Exam Question 324

    A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.
    What should the project manager do first?
  • PMP Exam Question 325

    we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
    What should the project manager do?