PMP Exam Question 341

A project manager has been assigned to a new project. There is one team member who never says anything during meetings. After meetings, however, the team member sends detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
  • PMP Exam Question 342

    A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
    What should the project manager do next?
  • PMP Exam Question 343

    An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.
    What should that project manager have done first in order to avoid this situation?
  • PMP Exam Question 344

    A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,
    * Actual progress = 2 units
    * Planned progress = 3 units
    * Actual cost (AC) = 2 units
    * Budgeted cost = 3 units
    What statement should the project manager make to the project steering committee?
  • PMP Exam Question 345

    Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
    How should the agile project leader resolve this situation?